Tap Comstock - Corral substation interconnection queue

2 active projects totalling 372.3 MW in the ERCOT queue.

2active projects
372.3active MW
2total filed
Queue IDProjectkVMWResourceStatus
26INR0419 Lone Bow Solar 138 277.5 Solar SS Started, FIS Started, No IA
25INR0546 VISOL 1 SOLAR 138 94.8 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.