tap Claytonville – Phantom Hill Circuit 2 substation interconnection queue

5 active projects totaling 390 MW in the ERCOT queue.

5 ERCOT queue filings name tap Claytonville – Phantom Hill Circuit 2 as the point of interconnection, all in Fisher County, TX.

Target commercial operation date as filed: Sep 2027 (5 filings). 5 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Innovative Solar 245, LLC (5 filings).

5active projects
390active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
21INR0031 Indigo Solar 345 150 Solar SS Completed, FIS Started, IA Sep 2027
24INR0496 Indigo Storage 345 60 Battery SS Completed, FIS Started, IA Sep 2027
25INR0528 Indigo Storage 2 345 60 Battery SS Completed, FIS Started, IA Sep 2027
25INR0529 Indigo Storage 3 345 60 Battery SS Completed, FIS Started, IA Sep 2027
25INR0530 Indigo Storage 4 345 60 Battery SS Completed, FIS Started, IA Sep 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Fisher County, TX

All 13 ERCOT queue filings in Fisher County, TX.