Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Starr County. First named in the release with data as of May 12, 2023.

Starrcounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Starr, TX: ERCOT queue, 21 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Roma: Build new 138 kV terminal
Bordertown BESS interconnection to Roma Station on Roma Switch to Rio Grande City
ERCOT project 73448
AEP TCC
Tier 4
Planned
Future tab
138 Sep 2027 Roma
Starr County
Roma

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202673448Moved between tabsCurrent-year planned → Future
June 1, 202673448Projected in-service dateSep 2026 → Sep 2027
February 1, 202673448Moved between tabsFuture → Current-year planned
February 1, 202673448Projected in-service dateOct 2026 → Sep 2026
October 1, 202573448Moved between tabsCurrent-year planned → Future
October 1, 202573448Projected in-service dateSep 2025 → Oct 2026
June 1, 202573448Moved between tabsFuture → Current-year planned
June 1, 202573448Projected in-service dateMay 2025 → Sep 2025
October 1, 202473448Projected in-service dateDec 2024 → May 2025
June 1, 202473448Projected in-service dateOct 2024 → Dec 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first