Mistflower Energy Center Storage
ERCOT queue ID 30INR0089
| Queue ID | 30INR0089 |
|---|---|
| Project name | Mistflower Energy Center Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Odysseus – Bluff Creek |
| Point of interconnection | Tap 345kV 60072 Odysseus – 60040 Bluff Creek |
| County | Runnels |
| State | TX |
| Voltage | 345 kV |
| Capacity | 312.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2030-06-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Mistflower Energy Center LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 46104 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.