8 active projects totalling 1,803.3 MW in the ERCOT queue.

8active projects
1,803.3active MW
8total filed
Queue IDProjectkVMWResourceStatus
30INR0088 Mistflower Energy Center Solar 345 401.6 Solar SS Completed, FIS Started, No IA
30INR0089 Mistflower Energy Center Storage 345 312.9 Battery SS Completed, FIS Started, No IA
28INR0198 Winters Glow Solar 345 301.6 Solar SS Completed, FIS Started, No IA
30INR0076 Zuma Solar 345 201.4 Solar SS Completed, FIS Started, No IA
29INR0210 Sawtooth Solar 345 201.4 Solar SS Completed, FIS Started, No IA
28INR0199 Winters Glow Storage 345 155.2 Battery SS Completed, FIS Started, No IA
19INR0035 Norton Solar 138 128.5 Solar SS Completed, FIS Completed, IA
24INR0485 Rutile BESS 138 100.7 Battery SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.