Tierra Loma Solar
ERCOT queue ID 29INR0279
| Queue ID | 29INR0279 |
|---|---|
| Project name | Tierra Loma Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap # ROCK DRAW - # NORTH MCCAMEY ckt 1 |
| Point of interconnection | Tap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1 |
| County | Crane |
| State | TX |
| Voltage | 345 kV |
| Capacity | 250 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2029-09-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Tierra Loma Solar, LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 46157 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.