Substation Scout

Star Of Texas Solar

ERCOT queue ID 29INR0188

Queue ID29INR0188
Project nameStar Of Texas Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationFort Stockton Switch
Point of interconnection60152 Fort Stockton Switch 345kV
CountyPecos
StateTX
Voltage345 kV
Capacity415 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-07-01
Source datasetlarge

Additional filed fields

Interconnecting EntityBOULEVARD ASSOCIATES, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45971
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.