Meitner 2 Wind
ERCOT queue ID 29INR0103
Meitner 2 Wind (29INR0103) is listed in the ERCOT interconnection queue as a 709.1 MW wind project in Gray County, TX. The filing names Gray Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on September 2, 2025.
| Queue ID | 29INR0103 |
|---|---|
| Project name | Meitner 2 Wind |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Gray Substation |
| Point of interconnection | 79000 Gray Substation 345kV |
| County | Gray |
| State | TX |
| Voltage | 345 kV |
| Capacity | 709.1 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2028-06-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Gray Substation substation: 2 requests in the ERCOT queue, 2 active totaling 1,418.1 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 26INR0113 | Meitner Wind | 709 | Wind | SS Completed, FIS Started, IA |
Gray, TX: 3 requests in the ERCOT queue, 3 active totaling 2,120.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | IP Meitner, LLC |
|---|---|
| CDR reporting zone | PANHANDLE |
| Fuel code | WIN |
| Technology code | WT |
| Screening study complete | 2025-09-02 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.