Palomino Solar
ERCOT queue ID 29INR0056
| Queue ID | 29INR0056 |
|---|---|
| Project name | Palomino Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Monticello - Sulphur Springs |
| Point of interconnection | Tap 345kV 1695 Monticello - 1697 Sulphur Springs |
| County | Hopkins |
| State | TX |
| Voltage | 345 kV |
| Capacity | 301.2 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Palomino Renewables |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 45670 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.