Buzios BESS SLF

ERCOT queue ID 29INR0021

Queue ID29INR0021
Project nameBuzios BESS SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Cottonwood - White River Ckt 2
Point of interconnectionTap 345kV 59904 Cottonwood - 23922 White River Ckt 2
CountyMotley
StateTX
Voltage345 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-07-01
Source datasetlarge

Additional filed fields

Interconnecting EntityBuzios Energy Storage, LLC
Cdr ZonePANHANDLE
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45839

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.