Substation Scout

Cattle Drive Solar

ERCOT queue ID 29INR0013

Queue ID29INR0013
Project nameCattle Drive Solar
Status (as published)SS Completed, FIS Started, IA
SubstationNorth McCamey
Point of interconnection76000 North McCamey 345kV
CountyCrane
StateTX
Voltage345 kV
Capacity307 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetlarge

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting EntityCattle Drive Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Ia Signed46020
Screening Study Complete45545
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.