Vertus Energy Storage 2
ERCOT queue ID 28INR0490
| Queue ID | 28INR0490 |
|---|---|
| Project name | Vertus Energy Storage 2 |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | TNMAINLAND1 |
| Point of interconnection | 38830 TNMAINLAND1 138 KV |
| County | Galveston |
| State | TX |
| Voltage | 138 kV |
| Capacity | 204.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2028-02-15 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Vertus Energy Storage 2 LLC |
|---|---|
| Cdr Zone | HOUSTON |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 46129 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.