Mission Station Energy Storage I
ERCOT queue ID 28INR0474
| Queue ID | 28INR0474 |
|---|---|
| Project name | Mission Station Energy Storage I |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap (Bus #) SPRUCE – (Bus #) VON_ROSE Ckt 1 |
| Point of interconnection | Tap 345kV (Bus #5400) SPRUCE – (Bus #5475) VON_ROSE Ckt 1; |
| County | Bexar |
| State | TX |
| Voltage | 345 kV |
| Capacity | 375 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2030-05-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Mission Station LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 46150 |