Bexar, TX interconnection queue

23 active projects totalling 5,169.6 MW in the ERCOT queue.

23active projects
5,169.6active MW
23total filed
Queue IDProjectkVMWResourceStatus
29INR0173 Howard Road BESS 345 617.6 Battery SS Completed, FIS Started, No IA
27INR0082 Orbit Energy Storage 345 501.9 Battery SS Completed, FIS Started, No IA
27INR0294 Bernice Energy Storage 138 402.8 Battery SS Completed, FIS Started, No IA
28INR0474 Mission Station Energy Storage I 345 375 Battery SS Completed, FIS Started, No IA
28INR0475 Mission Station Energy Storage II 345 375 Battery SS Completed, FIS Started, No IA
22INR0423 Quela BESS 138 301.4 Battery SS Completed, FIS Started, No IA
28INR0390 Horsepower BESS 138 257.5 Battery SS Completed, FIS Started, No IA
23INR0467 Lavender Storage Project 138 231.9 Battery SS Completed, FIS Started, IA
23INR0479 Taormina Storage 138 231.9 Battery SS Completed, FIS Started, IA
27INR0393 Ferdinand Grid BESS II 138 208.1 Battery SS Completed, FIS Started, No IA
25INR0346 Cado Storage 138 205.5 Battery SS Completed, FIS Started, No IA
28INR0020 Caracara Energy Storage Center 138 203 Battery SS Completed, FIS Started, No IA
28INR0024 Padua Grid BESS Unit 3 138 201.4 Battery SS Completed, FIS Completed, IA
26INR0331 RUSH ESS 345 201.3 Battery SS Completed, FIS Started, No IA
27INR0180 Otter BESS 138 157.1 Battery SS Completed, FIS Started, No IA
23INR0207 El Patrimonio Solar 138 152.3 Solar SS Completed, FIS Completed, IA
27INR0342 Dorsey Road BESS 138 150.4 Battery SS Completed, FIS Started, No IA
26INR0330 Alamo City BESS 138 128.2 Battery SS Completed, FIS Started, IA
24INR0392 Riverwalk BESS 138 120 Battery SS Completed, FIS Started, No IA
24INR0108 Louisa Energy Storage 138 102.8 Battery SS Completed, FIS Started, IA
25INR0531 CPS Energy AvR1CT2 Rotor Replacement 345 23.2 Gas SS Completed, FIS Completed, No IA
24INR0427 CPS AvR CT1 Rotor Replacement 345 11.3 Gas SS Completed, FIS Completed, No IA
26INR0702 Bexar Martinez BESS n/r 10 Battery In Queue

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.