Nabla Energy Storage II
ERCOT queue ID 28INR0466
| Queue ID | 28INR0466 |
|---|---|
| Project name | Nabla Energy Storage II |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Double Tap Parker () - Benbrook ( and ) DCKT |
| Point of interconnection | Double Tap 345kV Parker (1436) - Benbrook (1873 and 1869) DCKT |
| County | Parker |
| State | TX |
| Voltage | 345 kV |
| Capacity | 750 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2029-09-17 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Nabla Park LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 46034 |
| Air Permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.