Substation Scout

Parker, TX interconnection queue

4 active projects totalling 2,222.2 MW in the ERCOT queue.

4active projects
2,222.2active MW
4total filed
Queue IDProjectkVMWResourceStatus
27INR0571 Nabla Energy Storage I 345 750 Battery SS Completed, FIS Started, No IA
28INR0466 Nabla Energy Storage II 345 750 Battery SS Completed, FIS Started, No IA
23INR0368 Rocking X Solar 345 602.2 Solar SS Completed, FIS Started, No IA
26INR0498 Buckaroo BESS 138 120 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.