Substation Scout

Tolivar Power Plant Phase 2

ERCOT queue ID 28INR0413

Queue ID28INR0413
Project nameTolivar Power Plant Phase 2
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Saltdraw- COWPEN
Point of interconnectionTap 138 KV 38055 Saltdraw-38043 COWPEN
CountyReeves
StateTX
Voltage138 kV
Capacity224.5 MW
Resource (as published)GAS/IC
Resource categoryGas (normalised for filtering)
Target commercial operation2027-09-29
Source datasetlarge

Additional filed fields

Interconnecting EntityPecos Power Plant, LLC
Cdr ZoneWEST
Fuel CodeGAS
Technology CodeIC
Ia Signed46126
Screening Study Complete45943
Fis Approved46078
Air Permit46108
Water Availability46190

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.