Tolivar Power Plant Phase 2

ERCOT queue ID 28INR0413

Tolivar Power Plant Phase 2 (28INR0413) is listed in the ERCOT interconnection queue as a 224.5 MW gas project in Reeves County, TX. The filing names Tap Saltdraw- COWPEN as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of September 29, 2027. It records the screening study as complete on October 13, 2025, the full interconnection study as approved on February 25, 2026 and the interconnection agreement as signed on April 14, 2026.

Queue ID28INR0413
Project nameTolivar Power Plant Phase 2
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Saltdraw- COWPEN
Point of interconnectionTap 138 KV 38055 Saltdraw-38043 COWPEN
CountyReeves
StateTX
Voltage138 kV
Capacity224.5 MW
Resource (as published)GAS/IC
Resource categoryGas (normalized for filtering)
Target commercial operation2027-09-29
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Reeves, TX: 27 requests in the ERCOT queue, 24 active totaling 8,349.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityPecos Power Plant, LLC
CDR reporting zoneWEST
Fuel codeGAS
Technology codeIC
Interconnection agreement signed2026-04-14
Screening study complete2025-10-13
Full interconnection study approved2026-02-25
Air permit2026-03-27
Water availability2026-06-17

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.