Substation Scout

Yellow Leaf II BESS

ERCOT queue ID 28INR0412

Queue ID28INR0412
Project nameYellow Leaf II BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap CRANDALL1_8 - KAUFMN_8
Point of interconnectionTap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8
CountyKaufman
StateTX
Voltage138 kV
Capacity205.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-09-25
Source datasetlarge

Additional filed fields

Interconnecting EntityYellow Leaf Energy Storage LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45939

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.