Substation Scout

Kaufman, TX interconnection queue

16 active projects totalling 2,075.3 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).

16active projects
2,075.3active MW
18total filed
Queue IDProjectkVMWResourceStatus
25INR0090 Tempesta BESS n/r 600 Battery Inactive
25INR0089 Tempesta n/r 443 Solar Inactive
26INR0086 Solarville Solar SLF 345 402.9 Solar SS Completed, FIS Started, No IA
24INR0339 Mystic Springs Renewable Energy Solar SLF 345 258.8 Solar SS Completed, FIS Completed, IA
22INR0552 Sowers Storage 138 208.9 Battery SS Completed, FIS Started, IA
28INR0412 Yellow Leaf II BESS 138 205.7 Battery SS Completed, FIS Started, No IA
24INR0303 Erika Solar 345 200.5 Solar SS Completed, FIS Completed, IA
29INR0250 Slash Pine Storage 138 200 Battery SS Completed, FIS Started, No IA
26INR0502 Fudge Ranch BESS 138 104 Battery SS Completed, FIS Started, No IA
27INR0455 Yellow Leaf Solar 138 103.2 Solar SS Completed, FIS Started, No IA
27INR0456 Yellow Leaf BESS 138 103.1 Battery SS Completed, FIS Started, No IA
27INR0531 Erika BESS 345 100 Battery SS Completed, FIS Started, No IA
23INR0222 Sunbelt Solar 138 81.5 Solar SS Completed, FIS Started, No IA
22INR0426 LUBIO SOLAR 138 54.7 Solar SS Completed, FIS Started, IA
23INR0409 Sunbelt Storage 138 52 Battery SS Completed, FIS Started, No IA
24INR0340 Mystic Springs Renewable Energy Storage SLF 345 0 Battery SS Completed, FIS Completed, No IA
28INR0431 Solarville Wind SLF 345 0 Wind SS Completed, FIS Started, No IA
28INR0432 Solarville BESS SLF 345 0 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.