Ouroboros Grid BESS 1
ERCOT queue ID 28INR0397
Ouroboros Grid BESS 1 (28INR0397) is listed in the ERCOT interconnection queue as a 200.8 MW battery project in Cameron County, TX. The filing names POIB: # Chalybe (expansion of the # Chalybe – to be connected by double circuit line to # Palmito ) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of June 1, 2028. It records the screening study as complete on October 22, 2025.
| Queue ID | 28INR0397 |
|---|---|
| Project name | Ouroboros Grid BESS 1 |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | POIB: # Chalybe (expansion of the # Chalybe – to be connected by double circuit line to # Palmito ) |
| Point of interconnection | POIB: #88337 Chalybe 345 kV (expansion of the #8735 Chalybe 138 kV – to be connected by double circuit line to #79500 Palmito 345 kV) |
| County | Cameron |
| State | TX |
| Voltage | 345 kV |
| Capacity | 200.8 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-06-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Cameron, TX: 32 requests in the ERCOT queue, 30 active totaling 8,649.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Ouroboros Grid BESS Unit 1 |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2025-10-22 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.