ERCOT queue ID 28INR0395

Queue ID28INR0395
Project nameTreehouse Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationTap the Jewett (#) - Singleton (#) line, ONCOR
Point of interconnectionTap the 345 kV Jewett (#3390) - Singleton (#44645) line, ONCOR
CountyGrimes
StateTX
Voltage345 kV
Capacity209.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-11-13
Source datasetlarge

Additional filed fields

Interconnecting EntityTreehouse Solar, LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45956