Sagebrush Wind (28INR0386) is listed in the ERCOT interconnection queue as a 200.5 MW wind project in Nolan County, TX. The filing names TAP SWEETWATER EAST - CENTRAL BLUFF CKT2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 1, 2029. It records the screening study as complete on October 6, 2025.

Queue ID28INR0386
Project nameSagebrush Wind
Status (as published)SS Completed, FIS Started, No IA
SubstationTAP SWEETWATER EAST - CENTRAL BLUFF CKT2
Point of interconnectionTAP 345KV 11420 SWEETWATER EAST - 11406 CENTRAL BLUFF CKT2
CountyNolan
StateTX
Voltage345 kV
Capacity200.5 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2029-12-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Nolan, TX: 18 requests in the ERCOT queue, 18 active totaling 4,440.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityACE DevCo NC, LLC
CDR reporting zoneWEST
Fuel codeWIN
Technology codeWT
Screening study complete2025-10-06
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first