Substation Scout

Barranca Wind 1

ERCOT queue ID 28INR0375

Queue ID28INR0375
Project nameBarranca Wind 1
Status (as published)SS Completed, FIS Started, No IA
SubstationTap the CENIZO (#) - DELSOL (#) line
Point of interconnectionTap the 345 kV CENIZO (#80225) - DELSOL (#80307) line
CountyJim Hogg
StateTX
Voltage345 kV
Capacity300.9 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2028-06-01
Source datasetlarge

Additional filed fields

Interconnecting EntityBarranca Wind Energy, LLC
Cdr ZoneSOUTH
Fuel CodeWIN
Technology CodeWT
Screening Study Complete45936
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.