Substation Scout

Barkley Creek Solar

ERCOT queue ID 28INR0324

Queue ID28INR0324
Project nameBarkley Creek Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Line from Russel Gap Switch (Bus# ) - Killeen Switch (Bus# )
Point of interconnectionTap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch (Bus# 3422)
CountyLampasas
StateTX
Voltage345 kV
Capacity312.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-10-15
Source datasetlarge

Additional filed fields

Interconnecting Entity174 Power Global Properties, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45930
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.