Substation Scout

Altair Energy Storage

ERCOT queue ID 28INR0321

Queue ID28INR0321
Project nameAltair Energy Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationTap on ALTAIR (bus# ) to STAFFORD HILL (bus# )
Point of interconnectionTap on 138 kV ALTAIR (bus# 78118) to STAFFORD HILL (bus# 78520)
CountyColorado
StateTX
Voltage138 kV
Capacity201.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-03-31
Source datasetlarge

Additional filed fields

Interconnecting EntityAltair Energy Storage
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45857

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.