Margay Energy Storage
ERCOT queue ID 28INR0295
Margay Energy Storage (28INR0295) is listed in the ERCOT interconnection queue as a 101.3 MW battery project in Brazoria County, TX. The filing names Tap Mykawa - Telephone Ckt 06 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of April 10, 2029. It records the screening study as complete on May 20, 2025, the full interconnection study as approved on November 13, 2025 and the interconnection agreement as signed on December 26, 2025.
| Queue ID | 28INR0295 |
|---|---|
| Project name | Margay Energy Storage |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Mykawa - Telephone Ckt 06 |
| Point of interconnection | Tap 138kV 42750 Mykawa - 48353 Telephone Ckt 06 |
| County | Brazoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 101.3 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-04-10 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | PowerPulse LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-12-26 |
| Screening study complete | 2025-05-20 |
| Full interconnection study approved | 2025-11-13 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.