Substation Scout

Rio Vista Solar

ERCOT queue ID 28INR0260

Queue ID28INR0260
Project nameRio Vista Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # PigCreek4A – # Solstice4A
Point of interconnectionTap 138kV #60393 PigCreek4A – #60385 Solstice4A
CountyPecos
StateTX
Voltage138 kV
Capacity553.7 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityRio Vista Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45917
Water AvailabilityNot Required