ERCOT queue ID 28INR0160

Queue ID28INR0160
Project nameNeal Solar
Status (as published)SS Completed, FIS Started, No IA
Substationtap of CHARMERP4A - South Lane City
Point of interconnectiontap of 138kV 8750 CHARMERP4A - 8127 South Lane City
CountyWharton
StateTX
Voltage138 kV
Capacity146.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-04-03
Source datasetlarge

Additional filed fields

Interconnecting EntityCH Neal Solar LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45892
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.