| Queue ID | 28INR0111 |
|---|---|
| Project name | Biggs Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | # Bow Wood |
| Point of interconnection | #76006 Bow Wood 345 kV |
| County | McCulloch |
| State | TX |
| Voltage | 345 kV |
| Capacity | 400 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-11-15 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Biggs Solar Farm, LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 45583 |
| Water Availability | Not Required |