Substation Scout

McCulloch, TX interconnection queue

3 active projects totalling 750.8 MW in the ERCOT queue.

3active projects
750.8active MW
3total filed
Queue IDProjectkVMWResourceStatus
28INR0111 Biggs Solar 345 400 Solar SS Completed, FIS Started, No IA
28INR0110 Biggs BESS 345 200 Battery SS Completed, FIS Started, No IA
27INR0593 Pecan Ridge 69 150.8 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.