Biggs BESS
ERCOT queue ID 28INR0110
| Queue ID | 28INR0110 |
|---|---|
| Project name | Biggs BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Bow Wood |
| Point of interconnection | 76006 Bow Wood 345 kV |
| County | McCulloch |
| State | TX |
| Voltage | 345 kV |
| Capacity | 200 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2029-06-16 |
| Source dataset | large |
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting Entity | Biggs Battery Facility, LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45583 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.