Substation Scout

Caracara Energy Storage Center

ERCOT queue ID 28INR0020

Queue ID28INR0020
Project nameCaracara Energy Storage Center
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Cagnon - Potranco
Point of interconnectionTap 138kV 5055 Cagnon - 5346 Potranco
CountyBexar
StateTX
Voltage138 kV
Capacity203 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-08-01
Source datasetlarge

Additional filed fields

Interconnecting EntityFRESH AIR ENERGY II, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45509

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.