Limitless Energy Hub I
ERCOT queue ID 27INR0581
Limitless Energy Hub I (27INR0581) is listed in the ERCOT interconnection queue as a 1,238.3 MW gas project in Wilbarger County, TX. The filing names Tap RILEY7A - EDITHCLA7B. as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of December 1, 2028. It records the screening study as complete on January 12, 2026 and the interconnection agreement as signed on December 31, 2025.
| Queue ID | 27INR0581 |
|---|---|
| Project name | Limitless Energy Hub I |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap RILEY7A - EDITHCLA7B. |
| Point of interconnection | Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B. |
| County | Wilbarger |
| State | TX |
| Voltage | 345 kV |
| Capacity | 1,238.3 MW |
| Resource (as published) | GAS/CC |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2028-12-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap RILEY7A - EDITHCLA7B. substation: 2 requests in the ERCOT queue, 2 active totaling 2,476.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 27INR0582 | Limitless Energy Hub II | 1,238.3 | Gas | SS Completed, FIS Started, IA |
Wilbarger, TX: 24 requests in the ERCOT queue, 21 active totaling 8,450.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Limitless Energy Hub I LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | GAS |
| Technology code | CC |
| Interconnection agreement signed | 2025-12-31 |
| Screening study complete | 2026-01-12 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.