Trailblazer Solar

ERCOT queue ID 27INR0578

Queue ID27INR0578
Project nameTrailblazer Solar
Status (as published)SS Completed, FIS Started, No IA
Substation# Sweetwater East Switch
Point of interconnection#11420 Sweetwater East Switch 345 kV
CountyNolan
StateTX
Voltage345 kV
Capacity323 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-12
Source datasetlarge

Additional filed fields

Interconnecting EntityTrailblazer Infrastructure LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete46188
Water AvailabilityNot Required