Silver Hills Windpower
ERCOT queue ID 27INR0512
| Queue ID | 27INR0512 |
|---|---|
| Project name | Silver Hills Windpower |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Prong Moss Switch |
| Point of interconnection | 10066 Prong Moss Switch 138kV |
| County | Howard |
| State | TX |
| Voltage | 138 kV |
| Capacity | 54.1 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2029-06-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Silver Hills Windpower, LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | WIN |
| Technology Code | WT |
| Screening Study Complete | 45857 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.