Substation Scout

Coati Energy Storage

ERCOT queue ID 27INR0436

Coati Energy Storage (27INR0436) is listed in the ERCOT interconnection queue as a 202.8 MW battery project in Harris County, TX. The filing names Bus # , Humble as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of June 15, 2029. It records the screening study as complete on March 17, 2025.

Queue ID27INR0436
Project nameCoati Energy Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationBus # , Humble
Point of interconnectionBus # 40830, Humble, 138 kV
CountyHarris
StateTX
Voltage138 kV
Capacity202.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-06-15
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityPowerPulse LLC
CDR reporting zoneHOUSTON
Fuel codeOTH
Technology codeBA
Screening study complete2025-03-17

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first