Pez Rojo BESS
ERCOT queue ID 27INR0245
Pez Rojo BESS (27INR0245) is listed in the ERCOT interconnection queue as a 217.2 MW battery project in Harris County, TX. The filing names Tap # Chamon - # King as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of February 1, 2029. It records the screening study as complete on September 23, 2024 and the interconnection agreement as signed on May 1, 2026.
| Queue ID | 27INR0245 |
|---|---|
| Project name | Pez Rojo BESS |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap # Chamon - # King |
| Point of interconnection | Tap 138 kV #40260 Chamon - #40912 King |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 217.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-02-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Pez Rojo BESS, LLC |
|---|---|
| CDR reporting zone | HOUSTON |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2026-05-01 |
| Screening study complete | 2024-09-23 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.