Leopard BESS
ERCOT queue ID 27INR0224
Leopard BESS (27INR0224) is listed in the ERCOT interconnection queue as a 264.2 MW battery project in Victoria County, TX. The filing names Beecher as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of February 28, 2029. It records the screening study as complete on August 5, 2024 and the interconnection agreement as signed on June 9, 2025.
| Queue ID | 27INR0224 |
|---|---|
| Project name | Leopard BESS |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Beecher |
| Point of interconnection | 8721 Beecher 138 kV |
| County | Victoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 264.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-02-28 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Victoria, TX: 22 requests in the ERCOT queue, 17 active totaling 5,382.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Bobcat Energy Center, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-06-09 |
| Screening study complete | 2024-08-05 |
| Air permit | Not Required |
| Water availability | 2025-08-08 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.