Substation Scout

Chacon Creek

ERCOT queue ID 27INR0206

Queue ID27INR0206
Project nameChacon Creek
Status (as published)SS Completed, FIS Started, No IA
Substation(#) LYTLE4A
Point of interconnection(#8962) LYTLE4A 138KV
CountyMedina
StateTX
Voltage138 kV
Capacity189 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-10-31
Source datasetlarge

Additional filed fields

Interconnecting EntityCattlemen BESS LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45462

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.