Medina, TX interconnection queue
7 active projects totalling 955.9 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).
7active projects
955.9active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 28INR0392 | Devine Mary BESS | 138 | 200.6 | Battery | SS Completed, FIS Started, No IA |
| 27INR0206 | Chacon Creek | 138 | 189 | Battery | SS Completed, FIS Started, No IA |
| 29INR0152 | Ranger BESS | 138 | 155.2 | Battery | SS Completed, FIS Started, No IA |
| 27INR0203 | Dunlay Solar | 138 | 150.5 | Solar | SS Completed, FIS Started, No IA |
| 27INR0437 | Hondo Arroyo Storage | 138 | 100.7 | Battery | SS Completed, FIS Started, No IA |
| 25INR0610 | Adam Bryant BESS | 138 | 99.5 | Battery | SS Completed, FIS Started, No IA |
| 27INR0301 | Hondo Arroyo Solar | 138 | 60.4 | Solar | SS Completed, FIS Started, No IA |
| 20INR0025 | Spinel Solar | n/r | 30 | Solar | Inactive |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.