Trenno BESS
ERCOT queue ID 27INR0173
| Queue ID | 27INR0173 |
|---|---|
| Project name | Trenno BESS |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap Godley - Carmichael |
| Point of interconnection | Tap 138kV 2281 Godley - 2888 Carmichael |
| County | Johnson |
| State | TX |
| Voltage | 138 kV |
| Capacity | 202.6 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2027-09-13 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | JSB1, LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | OTH |
| Technology Code | BA |
| Ia Signed | 45887 |
| Screening Study Complete | 45412 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.