Johnson, TX interconnection queue
2 active projects totalling 628.6 MW in the ERCOT queue.
2active projects
628.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 24INR0075 | Blue Bird Solar | 345 | 426 | Solar | SS Completed, FIS Started, IA |
| 27INR0173 | Trenno BESS | 138 | 202.6 | Battery | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.