Comanche, TX interconnection queue

10 active projects totalling 2,797.6 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

10active projects
2,797.6active MW
11total filed
Queue IDProjectkVMWResourceStatus
27INR0365 Comanche BESS 345 614.4 Battery SS Completed, FIS Completed, IA
22INR0237 Dragan Solar 345 411 Solar SS Completed, FIS Started, No IA
22INR0400 Dragan Storage 345 408.3 Battery SS Completed, FIS Started, No IA
24INR0157 Merope BESS 345 402.4 Battery SS Completed, FIS Started, No IA
23INR0359 Crios BESS 138 205.5 Battery SS Completed, FIS Started, No IA
27INR0350 Saddle Horn Station BESS SLF 138 177.4 Battery SS Completed, FIS Completed, No IA
27INR0351 Saddle Horn Station Solar SLF 138 174.6 Solar SS Completed, FIS Completed, No IA
27INR0049 Darkwood Solar 345 152 Solar SS Completed, FIS Completed, IA
27INR0050 Darkwood BESS 345 150.5 Battery SS Completed, FIS Completed, IA
22INR0220 Lamkin Solar 69 101.5 Solar SS Completed, FIS Completed, IA
27INR0515 Paolo Sole Gustine Solar n/r 40.3 Solar Inactive

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.