Felix Storage

ERCOT queue ID 27INR0009

Felix Storage (27INR0009) is listed in the ERCOT interconnection queue as a 100.5 MW battery project in Wilbarger County, TX. The filing names The Riley Substation (#); AEP as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of July 31, 2027. It records the screening study as complete on March 30, 2023.

Queue ID27INR0009
Project nameFelix Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationThe Riley Substation (#); AEP
Point of interconnectionThe 345 kV Riley Substation (#6101); AEP
CountyWilbarger
StateTX
Voltage345 kV
Capacity100.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2027-07-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

The Riley Substation (#); AEP substation: 2 requests in the ERCOT queue, 2 active totaling 285.1 MW.

Queue IDProjectMWResourceStatus
27INR0007Felix East Solar184.6SolarSS Completed, FIS Started, IA

Wilbarger, TX: 24 requests in the ERCOT queue, 21 active totaling 8,450.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFelix 1, LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Screening study complete2023-03-30

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.