Hovey Solar 2
ERCOT queue ID 26INR0736
Hovey Solar 2 (26INR0736) is listed in the ERCOT interconnection queue as a 8.1 MW solar project in Pecos County, TX. The filing names Solstice as its point of interconnection. ERCOT lists its status as “In Queue”, with a target commercial operation date of September 15, 2026. It records the interconnection agreement as signed on December 26, 2013.
| Queue ID | 26INR0736 |
|---|---|
| Project name | Hovey Solar 2 |
| Status (as published) | In Queue |
| Substation | Solstice |
| Point of interconnection | 60385 Solstice 138 kV |
| County | Pecos |
| State | TX |
| Voltage | 138 kV |
| Capacity | 8.1 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2026-09-15 |
| Source dataset | small |
Same substation and county
Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | BARILLA SOLAR, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2013-12-26 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.