Substation Scout

Alamo Street BESS2

ERCOT queue ID 26INR0734

Alamo Street BESS2 (26INR0734) is listed in the ERCOT interconnection queue as a 10 MW battery project in Pecos County, TX. The filing names TSP Station Name: Alamo Street Sub TNP TSP as its point of interconnection. ERCOT lists its status as “In Queue”, with a target commercial operation date of March 30, 2027. It records the interconnection agreement as signed on February 1, 2023.

Queue ID26INR0734
Project nameAlamo Street BESS2
Status (as published)In Queue
SubstationTSP Station Name: Alamo Street Sub TNP TSP
Point of interconnectionTSP Station Name: Alamo Street Sub TNP TSP Station Code: ALAMO_ST Load Name / Load Transformer Name: ALAMO_2 Bus #: PTI Bus Number: 38331 Voltage (Transmission level kV): 138 Node (associated w/ load/load XFMR in NMMS): 9631
CountyPecos
StateTX
VoltageNot reported
Capacity10 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2027-03-30
Source datasetsmall

Same substation and county

Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityMomentum Pilsner, LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2023-02-01

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.