Alamo Street BESS2
ERCOT queue ID 26INR0734
Alamo Street BESS2 (26INR0734) is listed in the ERCOT interconnection queue as a 10 MW battery project in Pecos County, TX. The filing names TSP Station Name: Alamo Street Sub TNP TSP as its point of interconnection. ERCOT lists its status as “In Queue”, with a target commercial operation date of March 30, 2027. It records the interconnection agreement as signed on February 1, 2023.
| Queue ID | 26INR0734 |
|---|---|
| Project name | Alamo Street BESS2 |
| Status (as published) | In Queue |
| Substation | TSP Station Name: Alamo Street Sub TNP TSP |
| Point of interconnection | TSP Station Name: Alamo Street Sub TNP TSP Station Code: ALAMO_ST Load Name / Load Transformer Name: ALAMO_2 Bus #: PTI Bus Number: 38331 Voltage (Transmission level kV): 138 Node (associated w/ load/load XFMR in NMMS): 9631 |
| County | Pecos |
| State | TX |
| Voltage | Not reported |
| Capacity | 10 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-03-30 |
| Source dataset | small |
Same substation and county
Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Momentum Pilsner, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2023-02-01 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.