ERCOT queue ID 26INR0724

Monahans Power Gas (26INR0724) is listed in the ERCOT interconnection queue as a 18.2 MW gas project in Ward County, TX. The filing names Tap # Monahans Tap 2 to # Pecos Trail as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 16, 2030. It records the screening study as complete on December 2, 2025.

Queue ID26INR0724
Project nameMonahans Power Gas
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Monahans Tap 2 to # Pecos Trail
Point of interconnectionTap #1107 Monahans Tap 2 to #11117 Pecos Trail 138kV
CountyWard
StateTX
Voltage138 kV
Capacity18.2 MW
Resource (as published)GAS/IC
Resource categoryGas (normalized for filtering)
Target commercial operation2030-04-16
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Ward, TX: 13 requests in the ERCOT queue, 12 active totaling 3,247.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityLiberty Power Innovations LLC
CDR reporting zoneWEST
Fuel codeGAS
Technology codeIC
Screening study complete2025-12-02

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first