Fort Worth Power Core Bastrop Gas Plant

ERCOT queue ID 26INR0560

Fort Worth Power Core Bastrop Gas Plant (26INR0560) is listed in the ERCOT interconnection queue as a 506.4 MW gas project in Bastrop County, TX. The filing names Tap ZORN - AUSTROP as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 28, 2029. It records the screening study as complete on August 22, 2025.

Queue ID26INR0560
Project nameFort Worth Power Core Bastrop Gas Plant
Status (as published)SS Completed, FIS Started, No IA
SubstationTap ZORN - AUSTROP
Point of interconnectionTap 345kV 7042 ZORN - 7040 AUSTROP
CountyBastrop
StateTX
Voltage345 kV
Capacity506.4 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2029-09-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Bastrop, TX: 16 requests in the ERCOT queue, 14 active totaling 5,098.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFort Worth Power Core LLC
CDR reporting zoneSOUTH
Fuel codeGAS
Technology codeCC
Screening study complete2025-08-22
Air permit2024-12-20
Water availability2025-11-19

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.