Comanche Creek generating station
ERCOT queue ID 26INR0537
Comanche Creek generating station (26INR0537) is listed in the ERCOT interconnection queue as a 107 MW gas project in Pecos County, TX. The filing names TNCENTRY1_1 [] as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on September 23, 2024.
| Queue ID | 26INR0537 |
|---|---|
| Project name | Comanche Creek generating station |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | TNCENTRY1_1 [] |
| Point of interconnection | TNCENTRY1_1 [138 kV] ( 38431) |
| County | Pecos |
| State | TX |
| Voltage | 138 kV |
| Capacity | 107 MW |
| Resource (as published) | GAS/IC |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Longfellow Power LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | GAS |
| Technology code | IC |
| Screening study complete | 2024-09-23 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.