Electric E - West Texas Generation

ERCOT queue ID 26INR0529

Queue ID26INR0529
Project nameElectric E - West Texas Generation
Status (as published)SS Completed, FIS Started, No IA
Substation# ENPOD
Point of interconnection#11166 ENPOD 138kV
CountyLoving
StateTX
Voltage138 kV
Capacity43.6 MW
Resource (as published)GAS/GT
Resource categoryGas (normalised for filtering)
Target commercial operation2028-04-09
Source datasetlarge

Additional filed fields

Interconnecting EntityElectric E Power Marketing
Cdr ZoneWEST
Fuel CodeGAS
Technology CodeGT
Screening Study Complete45667

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.